Project lessons learned for running /x-wt-teams multi-agent epics in this repo. Read PROACTIVELY before planning or implementing any multi-wave epic (e.g. the Theme Batch / Theme Finalize epics, or an...
2026-07-16 — Theme Core (#2812) multi-wave /x-wt-teams run
What we set out to do
Implement a 10-sub-issue epic across 5 dependency-ordered waves via /, each sub-issue built by a worktree child agent, merged into a base branch, then merged to main.
Approach we tried first
Merged each child's branch as soon as its worktree looked done — commits present, working tree clean, package-scoped unit tests green — without waiting for the child's own completion report.
Told children to run
/(orlight- review /) as their self-review step and report back when done.codex- review
Why it went wrong (root cause)
"Tests pass + tree clean" is not "the agent is done." The child's mandated self-review had not finished. Merging on that signal pruned the worktree out from under a still-running review. Three sub-issues (#2822 engine, #2823 generator, #2825 dialog) were merged this way, and every one's review then surfaced a real bug — including a P1 last-write-wins race hole in the runtime switch engine that was a defect in the ADR's own algorithm. Each agent recovered only because it happened to open a follow-up branch; that was luck, not design.
Worktree child agents park on background reviews.
//light- review /launch codex as a background task and then wait for a completion notification. Inside a subagent that notification is delivered to the manager, not the child, so the child stalls — 6 of 7 children this run ended their turn parked ("waiting for the Monitor / codex review"), with work often left uncommitted. The manager only discovered this by inspecting each worktree directly, which is what pushed it toward the premature-merge workaround above. The two traps are one causal chain: parking → manager works around it by merging-on-inspection → premature merge.codex- review
What worked instead
Merge only on the child's explicit completion report (review applied + committed). When a child parks, resume it (
SendMessage) with: "you will NOT receive a background-review notification — run the review in the FOREGROUND, apply findings, COMMIT, then report." After that instruction, children came back with reviews actually applied (e.g. #2821), not abandoned.The manager runs the heavy checks on the merged base, because children structurally cannot: full
pnpm build, e2e,pnpm b4push, and anything that holds a port (dev servers) freeze the machine or blow token budgets. Every integration / zdtp / CI bug this run was invisible to package-scoped unit tests and surfaced only in the manager's full-build + e2e + deep-review passes on the merged base (missing barrel export → shippedroutes-srcbroke; a required payload field → SSRregistry is not iterable;configurePanelnot pushing zdtp overrides to:root; a flakynpm pack --jsonparse; a cold-CI timeout;_temp-resourcetripping the compatibility contract).
Watch for next time
If a child agent's last message is "waiting for the review / Monitor / codex to finish," it has parked — its self-review will never complete on its own. Resume it and force foreground review + commit-before-report. Better: bake "run self-review in the foreground; do NOT start a background review and await a notification — you won't get one" into the child prompt from the start.
If you're about to
git mergea child branch and remove its worktree, first confirm the child sent a completion report, not just that tests are green and the tree is clean. A clean tree with green package tests is the state a parked-mid-review agent is also in.Package-scoped unit tests passing tells you nothing about cross-package integration, SSR, or CI-job behavior. Before merging a wave to the parent, the manager must run the full site build and the e2e / drift / b4push gates on the merged base — children are barred from these (ports / freeze).
A required field added to a shared payload type (
RouteContextPayloadetc.) mid-epic is a breaking change for hosts that construct the payload themselves — normalize?? nulland keep the field optional, or the upgrade path throws at SSR.CI runs the full job command set, not the single-package suite you ran locally. Reproduce a red check by running the exact CI step commands (
pnpm test:packages, the lint-gate commands), notpnpm --filter <one-package> test._temp-resource/planning scratch is committed but "tooling ignores it" — it will trip content lint gates (compatibility contract, etc.) on every epic that carries it until Finalize deletes it. Exclude the prefix from the offending check rather than deleting the scratch.
Would-skip-if-redoing
Skip merging-on-green-tests. It saved no real time — every premature merge cost a follow-up branch + re-merge + re-verify, strictly more work than waiting for the report would have been.
Skip re-arming shell monitors with
status=as a loop variable in zsh —statusis read-only there and silently kills the monitor. Use a non-reserved name.